Acton (Murphy Pipelines)

Back to Case Studies

ATL successfully completed 7 crossings with an Iseki Unclemole. The crossings ranged from 50m up to 126m in length within London Clay. The scheme also involved constructing 10nr caisson shafts ranging from 3m ID to 2.4m ID, to drive and receive the machine into.