The 1500dia concrete sleeve was to allow 2 x 710mm dia plastic pipes to pass through (also as sleeves), with ultimately 2 x 500mm water mains then being housed within the sleeves. The 1500dia tunnel x 75m long will be installed as a pipe jack using a full faced TBM.
The drive pit was 6m x 4m in plan x 7m deep, with reception pit being 7.5m x 3.5m in plan x 5m deep. ATL installed these cofferdams with the aid of their own 36ton zero swing excavator, which was also used to lift the TBM in/out of cofferdam during the tunnelling works.
ATL’s own TBM with rock head was used to dig through the Phyllite ground, which it chewed through with ease, nearly doubling forecast production & saving 2 weeks on the tunnel operation alone.
ATL proposed to cast timber rails, set in concrete to gradient within the 1500 tunnel, to allow the twin 710mm plastic pipes to be slid along into position. ATL also proposed to install steel restraining bars (fabricated by ATL) within the tunnel to prevent the 710mm plastic pipes from floating when the tunnel void was pumped full of grout later. Both details worked very well & the pipes were installed successfully with no issues.
The client was extremely pleased with all the work carried out on this site with the contract programme being reduced by a total of 3 weeks.
“Pre-Construction, Active Tunnelling were engaged early to assist with the detailing of the water main / grouting details within the tunnel and provide technical submissions for Highways England approval.
During the Construction phase Active Tunnelling successfully completed installation on site in 10 weeks, 3 weeks ahead of programme with zero safety incidents.
Kier were pleased with Active’s performance and would be happy to engage with them again on future schemes”.
Kier Utility
Chiverton
£376k
13 Weeks